At this point we should have enough stuff to start setting up in the balcony area. Long cable runs should be started, but can't really leave the balcony due to there being an event in Central Hall on Saturday. We should attempt to get as much of the sound setup completed as possible at this point also.
At this point we should have enough stuff to start setting up in the balcony area. Long cable runs should be started, but can't really leave the balcony due to there being an event in Central Hall on Saturday. We should attempt to get as much of the sound setup completed as possible at this point also.
Note: Cable runs to the cameras can be completed on the Friday so long as they don't get in the way of the audience (which they shouldn't anyway).


As a general note, all Cables should be sensibly labelled at both ends '''''BEFORE''''' they are run, likewise all cables should be tested ahead of time.
As a general note, all Cables should be sensibly labelled at both ends '''''BEFORE''''' they are run, likewise all cables should be tested ahead of time.


On the Day of the Event, Sunday Week 8, we'll be setting up from about 12 and will require the following additional equipment in this rough order: